Due to flooding brought by Hurricane Irma, our progress was put to a halt. We received more than eight inches of rain at the site which put it, along with the roadway and all surrounding drainage ditches, underwater. This made any movement and water pumping near impossible.

Since then, we have been able to start pumping water again which has allowed clearing operations to proceed! Tree removals started on Monday, and we hope to start hauling trees off site later this week and remove stumps and grind on site.